Supporting Kiewit-Turner with New Denver VA Medical Center

Contracted with Kiewit-Turner, Farnsworth Group is serving as the Commissioning Specialist for the construction phase implementation of an Integrated Campus Commissioning Plan for the Department of Veterans Affairs Eastern Colorado Health Care System’s replacement medical center campus. The Aurora project comprises the new construction of three clinic buildings, two inpatient buildings, a diagnostic and treatment facility, a research building, an energy center, a connecting concourse and a parking structure. The seven buildings are connected by a spine and central utility plant for the entire VA campus.

  • The project has a combined area of more than 1 million SF and estimated construction cost of $1.3 billion. 
  • Anticipated completed date is January 23, 2018.