Crossroads Wind Power, LLC Crossroads Wind Farm

Farnsworth Group is providing surveying, transportation engineering, site design, and permitting services for the 60 MW Crossroads Wind Project consisting of 24 turbines and 4 miles of external transmission lines.
Design services will include 7 miles of County and Township Roadway improvements.
Transportation and site services for the Crossroads Wind Project includes:

  • Base map development
  • Assisted with road use agreement development
  • Transportation plan development
  • County and township highway evaluations (including drainage)
  • Pre-construction public roadway condition survey
  • Traffic Impact Analysis (TIA) report
  • State highway, county highway, and township roadway permit applications
  • Railroad permit applications
  • Coordination with railroad related to crossing improvements
  • Utility relocation coordination
  • Coordination meetings with road authorities
  • Project meetings
  • County highway and township roadway intersection improvement plans
  • Township roadway improvement plans – strengthening and widening including drainage
  • Private access road design including drainage
  • Turbine site designs
  • Lay down yard design and grading plans
  • 2D hydraulic site analysis
  • Site, private and public roadway bill of quantities
  • Site, private and public roadway technical specifications
  • Spill prevention, control and countermeasures plan (SPCC)
  • Limited construction administration and support

Marathon Petroleum, LP Commissioning of a Pipeline to Transport Natural Gas Liquids

Farnsworth Group assisted with the development of commissioning and hydrostatic test plans for the Utica Build-Out projects. The goal of these projects was to transport Utica natural gas liquids (NGL). Some of the projects included:

  • Expansion of three existing pipeline systems
  • A major facility expansion
  • Three minor facility expansions
  • Installation of a new 49-mile long 12-IN pipeline from Harpster, Ohio to Lima, Ohio.

Farnsworth Group teamed with the client during conceptual engineering of the project to begin developing high-level facility and mainline fill plans. These plans included first-operations plans for several new mainline pump units, provers, meters, control valves, sumps, DRA skids, and new large floating roof storage tanks. In total, 13 commissioning plans and a hydrostatic test plan were developed. We also assisted with the field engineering of the commissioning and hydrostatic test work – acting as liaison between project contractors and the client. Once the commissioning was completed, the movement of additional barrels began to flow across the expanded system.